In Value Stream, Should we include Spikes as spikes are a preparation for a story and has technical approach and not demo able.
In Value Stream, Should we include Spikes as spikes are a preparation for a story and has technical approach and not demo able.
4 answers0 replies
Comments (4)
Commenting on this post isn't available anymore. Contact the site owner for more info.
bottom of page
Hi Sid! Spikes are usually not part of the regular planned work. They are ad-hoc short-term experiments, tests or research, done only when needed, and done for the minimum sufficient and necessary, usually to make a better decision about something technical. They are not supposed to take a relevant amount of time, and should be timeboxed. I'd add them to the board just to create visibility for the entire team.